Nickel mines in Western Australia to become huge energy storage systems

BHP starts construction of one of the world's largest off-grid mining solar and battery energy storage systems at two nickel mines

Australia-based miner BHP has started construction on one of the world’s largest off-grid mining solar and battery energy storage systems at two nickel mines in Western Australia.

The $52 million Northern Goldfields Solar Project is being built and operated by global renewables group TransAlta Renewables, both companies announced on Wednesday, February 2.

The projects include a 27.4 Megawatt solar farm at Mount Keith, a 10.7 MW solar farm and a 10.1 MW battery at Leinster and will replace power that is currently supplied by diesel and gas. This will result in an estimated reduction of 54,000 tonnes of CO2 per year, BHP said, or a 12% reduction of scope 2 emissions (indirect emissions from the generation of purchased energy).

BHP and TransAlta have also entered into an agreement to identify potential wind sites for 40-50MW of capacity.

“The Northern Goldfields Solar Project is BHP’s first off-grid large-scale renewable energy project across our global operations and, significantly, will remove the equivalent of up to 23,000 combustion engine cars from the road every year, supporting our greenhouse gas reduction targets,” Jessica Farrell, BHP Nickel West Asset president said.

Farrell said that with this off-grid project, BHP was meeting its commitment to deliver sustainable low-carbon nickel to its customers. In July 2021, BHP signed an agreement to supply nickel to electric vehicle manufacturer Tesla Inc, marking another long-term supply deal with an emphasis on establishing a low-carbon supply chain. The partnership was formed with the ambition to promote sustainability within the mining and resources sector, with the two companies also collaborating on energy storage solutions.

Integrating renewable energy such as solar and winds farms into mining operations is a way for mining companies to cut emissions while increasing transparency in the supply chain. There are currently many projects at the beginning of the scaling stage, and due to the high energy demand from mines, there is a mutual interest from both renewable energy companies and miners to develop further projects in the off-grid mining sector.

What to read next
EV advocate Quentin Wilson talks myths, market trends and the road ahead
The disconnect between spodumene and lithium salts prices has become a major focus in the global battery raw materials market, as discussed at the 2025 Fastmarkets conference in Shanghai. Factors like new pricing mechanisms, spodumene auctions and shifting supply-demand trends highlight the need for improved risk management tools and price transparency.
The 2025 executive order on U.S. mineral production is a major step toward strengthening domestic supply chains and national security. By boosting domestic mineral production, it aims to reduce reliance on imports and ensure a secure future for critical industries. This order will shape the future of U.S. mining and its role in global markets.
The United States is taking steps to strengthen its critical mineral supply. This move focuses on boosting domestic production, improving supply chains, and addressing regulatory challenges. These efforts aim to enhance economic growth and reinforce national security.
After a consultation period, Fastmarkets has discontinued this price due to separate assessments for briquette and full plate nickel warrants being more reflective of the market. All short-term forecasts associated with this price (or these prices) produced by the Fastmarkets research team, if any, have also been discontinued. If you have any comments on the discontinuation […]
The initial consultation, which started on February 26, received mixed views on the trading quantities of the material as nickel matte output has been on a downtrend in the recent month, leading to slower spot liquidity. To properly to price a material with slowing liquidity, Fastmarkets has decided to extend the consultation period of the proposal […]